Thursday, November 24, 2022

CONSUMER COMPLAINT AGAINST BUILDER SEEKING REFUND

 


CONSUMER COMPLAINT AGAINST BUILDER SEEKING REFUND

The Consumer Protection Act, 1986 have undergone periodic changes vide several amendments and finally there has been a comprehensive changes in the Act and Consumer Protection Act 2019 is enacted.  The Consumer Commissions are flooded with cases against builders seeking various sorts of relief relating to possession, lapses, deficiency in service and more importantly, for seeking refund of the principal deposited along with due interest thereon, on account of delay in delivery of possession and also for seeking refund simpliciter owing to the delay in projects. It is a common knowledge, that, sometime the delay in construction is inordinate and therefore rather than seeking possession of the property, the consumer seeks refund of the sums paid. The law in this regard has evolved vastly, and despite some earlier hiccups, broad and clear periphery has now emerged. The Consumer Protection Act, though, shall only be limited to such consumer dispute which is as per the definition clause, the consumer dispute and that should not relate to a commercial dispute. The pith and substance of this article, though, shall revolve around the periphery of seeking only refund of amount, deposited towards allotment of flat or plot on account of delay in handing over possession.



To begin with, what is of worth reference is a recent Three (3) Judge Bench judgment of hon’ble Supreme Court reported as EXPERION DEVELOPERS PVT. LTD. VERSUS SUSHMA ASHOK SHIROOR[1]  It is held that When Statutes provide more than one judicial fora for effectuating a right or to enforce a duty-obligation, it is a feature of remedial choices offered by the State for an effective access to justice. Thus, whether one opts to approach RERA or Consumer Commissions constituted under the provisions of Consumer Protection Act is a choice of a consumer. It is also held that while interpreting statutes provisioning plurality of remedies, it is necessary for Courts to harmonize the provisions in a constructive manner.

The Supreme Court in Experion Developers (Supra) was pleased to dismiss the appeal preferred by the developer against order of  National Consumer Disputes Rederessal Commission (NCDRC), whereby refund and compensation to Consumer was directed for the failure of the builder to deliver possession of the apartment, within the time stipulated as per the Apartment Buyers Agreement was dismissed. The Supreme Court has held that the Commission is correct in its approach in holding that the clauses of the agreement are one-sided and that the Consumer is not bound to accept the possession of the apartment and can also seek refund of the amount deposited by her with interest - Commission has correctly exercised its power and jurisdiction in passing the directions for refund of the amount with interest.

Pertinently, the appeals were preferred under Section 23 of the Consumer Protection Act, 1986, which has arisen out of the judgment dated 19.06.2019 passed by the National Consumer Disputes Redressal Commission, whereunder, the Commission had directed the Developer to refund an amount of Rs. 2,06,41,379/- with interest @ 9% p.a. to the Respondent-Consumer for its failure to deliver possession of the apartment within the time stipulated as per the Apartment Buyers Agreement. The delay in delivery of possession was held unjustifiable. The interplay between the judicial remedies under the Act and the Real Estate (Regulation and Development) Act, 2016 and the remedial choices of a consumer under these statutes were delved in. It was held that the Commission created under the Act has the power to direct refund under Section 14 of the Act. The Consumer Protection Act (CPA) and the RERA Act 2016 does not exclude or contradict each other and therefore harmonious construction of the provisions shall be necessary with a view to achieve common object. The cross appeal was also preferred i.e one by the consumer also was preferred to the limited extent of seeking enhanced rate of interest.

As already delved in above, the power to direct refund of the amount and to compensate a consumer for the deficiency in not delivering the apartment as per the terms of Agreement is held within the jurisdiction of the Consumer Courts - A consumer can pray for refund of the money with interest and compensation. The consumer could also ask for possession of the apartment with compensation. The consumer can also make a prayer for both in the alternative. If a consumer prays for refund of the amount, without an alternative prayer, the Commission will recognize such a right and grant it, of course subject to the merits of the case. If a consumer seeks alternative reliefs, the Commission will consider the matter in the facts and circumstances of the case and will pass appropriate orders as justice demands.



The Supreme Court has earlier also held that Consumer Protection Act and the RERA Act neither exclude nor contradict each other - They are concurrent remedies operating independently and without primacy. [Referred to Imperia Structures Ltd v. Anil Patni[2] and IREO Grace Realtech (P) Ltd. V. Abhishek Khanna[3].

The Commission, in its judgment dated 19.06.2019, allowed the complaint after referring to Clause 10 (relating to the project completion period), Clause 11 (relating to the possession and conveyance of the apartment), as well as Clause 13 (relating to delay in possession). The Commission found that the agreement is one-sided, heavily loaded against the allottee and entirely in favour of the Developers. Following the decisions of the Supreme Court Pioneer Urban Land and Infrastructure Ltd. v. Govindan Raghvan[4], the Commission directed the Developer to refund the amount of Rs.2,36,15,726/- with interest @ 9% p.a.

It is against these findings and the consequential directions of the Commission that the cross appeals were filed –one by the Developer bearing Civil Appeal No. 6044/2019 and another by the Consumer being Civil Appeal No. 7149/2019, challenging the Commission's judgment to a limited extent for grant of an enhanced interest @ 24% p.a.

The following issues were for consideration before the hon’ble Supreme Court:

(i)            Whether the terms of the Apartment Buyers Agreement amount to an ‘unfair trade practice’ and whether the Commission is justified in not giving effect to the terms of Apartment Buyer’s Agreement as laid down in the Pioneer case?

(ii)           Whether the Commission has the power under the Consumer Protection Act, 1986 to direct refund of the amount deposited by the Consumer with interest?

(iii)          Whether the relief granted by the Commission require any modification to serve ends of justice?

 

The Supreme Court has in “Pioneer case”(Supra)  in somewhat similar factual as well as legal context held as under:

6.1 In the present case, admittedly the appellant builder obtained the occupancy certificate almost 2 years after the date stipulated in the apartment buyer’s agreement. As a consequence, there was a failure to hand over possession of the flat to the respondent flat purchaser within a reasonable period. The occupancy certificate was obtained after a delay of more than 2 years on 28-8-2018 during the pendency of the proceedings before the National Commission. In LDA v. M.K. Gupta, this Court held that when a person hires the services of a builder, or a contractor, for the construction of a house or a flat, and the same is for a consideration, it is a “service” as defined by Section 2(o) of the Consumer Protection Act, 1986. The inordinate delay in handing over possession of the flat clearly amounts to deficiency of service. In Fortune Infrastructure v. Trevor D’ Lima, this Court held that a person cannot be made to wait indefinitely for possession of the flat allotted to him, and is entitled to seek refund of the amount paid by him, along with compensation”.

 

The principle laid down in Pioneer’s case has been followed consistently in many cases where the terms of the Apartment Buyer’s Agreement were found to be one-sided and entirely loaded in favour of the Developer, and against the allottee at every step. The following are instances where the terms of the Apartment Buyer’s Agreement were found to be oppressive, constituting unfair trade practice and the Court has not given effect to such terms of the Agreement.

In NBCC (India) Ltd. v. Shri Ram Trivedi[5], the Supreme Court has found that the agreement fastening liability on the purchaser to pay simple interest @ 12% p.a. if he failed to pay installments on time and at the same time, if the seller failed to hand over the possession on time, he would have to pay compensation only @ of Rs. 2 per square feet would constitute an unfair trade practice. The Court held that a term of a contract would not be final and binding if it is shown that the flat purchasers have no option but to sign on the dotted line of a contract framed by the builders. The Supreme Court further held that Consumer Forums were empowered to award just and reasonable compensation as an incident of its power to direct removal of a deficiency in service; they are not constrained by the rate prescribed in the agreement. The Supreme Court has held that the compensation could be granted, even if possession had been delivered. The same principles are followed in a subsequent decision in DLF Home Developers Ltd. v. Capital Greens Flat Buyers Association & Ors[6].

A Three-Judge bench of Supreme Court in IREO Grace Realtech (P) Ltd. v. Abhishek Khanna & Ors (Supra) had occasion to deal with a delay compensation clause, which is similar to the clause in the present case, which provided that the Developer would be liable to pay delay compensation @ Rs 7.5 per square foot which works out to approximately 0.9 to 1% p.a. The Court held that this Clause was one-sided and entirely loaded in favour of the Developer and against the allottee. The Supreme Court had concluded that the powers of the Consumer Courts are in no manner constrained to declare a contractual term as unfair and one-sided as an incident of the power to discontinue unfair or restrictive trade practices. It was held:

“34. We are of the view that the incorporation of such one-sided and unreasonable clauses in the apartment buyer’s Agreement constitutes an unfair trade practice under Section 2(1)(r) of the Consumer Protection Act. Even under the1986 Act, the powers of the consumer fora were in no manner constrained to declare a contractual term as unfair or one-sided as an incident of the power to discontinue unfair or restrictive trade practices. An “unfair contract” has been defined under the 2019 Act, and powers have been conferred on the State Consumer Fora and the National Commission to declare contractual terms which are unfair, as null and void. This is a statutory recognition of a power which was implicit under the 1986 Act”.

 

That as regards the issue of payment of interest, as to what shall be the date of reckoning of payment of interest, the Supreme Court, has held that the date of respective deposits shall be the point wherefrom the interest shall be payable. It was thus held as under:

22.1 We are of the opinion that for the interest payable on the amount deposited to be restitutionary and also compensatory, interest has to be paid from the date of the deposit of the amounts. The Commission in the order impugned has granted interest from the date of last deposit. We find that this does not amount to restitution. Following the decision in DLF Homes Panchkula Pvt. Ltd. v. DS Dhanda and Ors. (2020) 16 SCC 318 and in modification of the direction issued by the Commission, we direct that the interest on the refund shall be payable from the dates of deposit. Therefore, the appeal filed by purchaser deserves to be partly allowed. The interests shall be payable from the dates of such deposits”.

 

The Supreme Court had upheld, though, payment of interest @9% per annum from the dates of respective deposits of installment.

In Wing Commander Arifur Rahman Khan and Aleya Sultana & Ors. v. DLF Southern Homes Private Limited[7]  the Supreme Court has held that there is no embargo on the award of compensation beyond the rate stipulated in the Apartment Buyer’s Agreement, where handing over the possession of the flat has been delayed. The Court observed that the Consumer Forums must take a robust and a common-sense approach by taking judicial notice of the fact that flat purchasers obtained loans and are required to pay EMIs to financial institutions for subserving their debts. The Delay Compensation Clause provided for Rs. 5 per square foot per month. This Court found that this stipulation is clearly one-sided and does not maintain a level platform or even reflect a bargain between the parties. The Court granted additional compensation @ 6% p.a. simple interest to each buyer therein, over and above the Delay Compensation Clause.

The Supreme Court has further held that a consumer invoking the jurisdiction of the Commission can seek such reliefs as he/she considers appropriate. A consumer can pray for refund of the money with interest and compensation. The consumer could also ask for possession of the apartment with compensation. The consumer can also make a prayer for both in the alternative. If a consumer prays for refund of the amount, without an alternative prayer, the Commission will recognize such a right and grant it, of course subject to the merits of the case. If a consumer seeks alternative reliefs, the Commission will consider the matter in the facts and circumstances of the case and will pass appropriate orders as justice demands. This position is similar to the mandate under Section 18 of the RERA Act[8].

The Supreme Court has clearly referred to the legal regime under the Consumer Protection Act, with a view to show that the Commission has the power and jurisdiction to direct return of money under Section 14 of the Consumer Protection Act, if a consumer so chooses. The freedom to choose the necessary relief is of the Consumer and it is the duty of the Courts to honour it.



                                   CONCLUSION

What thus emerges from the aforesaid discussion is that no fetter is attached to the power of Consumer Commissions and there is no conflict between RERA and Consumer Protection Act and a consumer may have the option to their remedy in whichever forum they prefer. Further, there is no embargo in a case against builder, as regards the necessity of seeking possession, notwithstanding delay. A consumer can seek possession of plot or flat as the case may be or refund of the sums paid as alternative, or compensation for delayed possession of the flat. The standard form agreement which contains one sided clauses has held to be not binding. As law has evolved, the one sided contract can also be negated by Consumer Commission. The sum ad substance of the law that has emerged is that unfair trade practices on the part of builder cannot be permitted. The one sided agreement proposed by the builder and eventually signed by the consumer is construed to be unfair trade practices and the periphery of relief or ambit of the Consumer Protection Act has considerably been widened since then.

                                                            ------

Anil K Khaware

Founder & Senior Associate

Societylawandjustice.com     

 



[1] 1  2022 LiveLaw (SC) 352.

[2] (2020) 10 SCC 783

[3] (2021) 3 SCC 241]

[4] (2019) 5 SCC 725

[5] (2021) 5 SCC 273

[6]  (2021) 5 SCC 537

[7] (2020) 16 SCC 512

[8]. THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016

 

No comments:

Post a Comment

SUCCESSION CERTIFICATE: LAW, JURISIDCTION OF COURTS & EFFECT

  Succession certificate: LAW, Jurisidction of Courts & EFFECT If a person dies intestate, leaving behind moveable properties such as ...