Tuesday, January 10, 2023

LAWS RELATED TO INVOCATION OF BANK GUARANTEE

 



Whether any fetter or string could be attached to the rights of encashment of bank guarantee by the beneficiary? The effort shall be to analyze the whole gamut of law as evolved in this regard over the years and the decisions arrived at and also whether the Courts or Arbitral Tribunal is empowered to pass judgment to that effect or not shall be the another dimension of the present write up. The overwhelming view in this regard shall have to be weighed in the backdrop of facts of several cases with a view to come to a plausible inference. Thus, the indulgence on precedents shall be the sine qua non. The dispute as regards encashment of bank guarantee shall also be an adjunct to principles of Section 73 & Section 74 of India Contract Act 1872, since the breach of contract shall be the precursor to any claim of encashment of bank guarantee.



LAW on encashment of bank guaranteeAND COMPENSATION

(A)   The law as regard breach and consequent compensation may have the substantive reference in a judgment reported as Fateh Chand Vs. Balkishan Das, (1964) 1 SCR 515, This is a a seminal judgment  where it was held that the jurisdiction of the Court of award compensation in case of breach is unqualified except as to the maximum amount stipulated so long as the compensation is reasonable. This imposes a duty upon the court to award compensation according to the settled principles. The phraseology of Section 74 was held to dispense with the proof of actual loss or damages but it did not justify the award of compensation when in consequence of the breach no legal injury at all has resulted. It was, thus, clearly held that a plaintiff has to prove a loss suffered by him in consequence of the breach of contract committed by the defendant. This legal position laid down by the Constitutional Bench of the Supreme Court is good law till date and, thus, any judgment of the Supreme Court of a Bench constituted of lesser number of Judges would, thus, have to be read in the context of the seminal pronouncement.

(B)    In Maula Bux Vs. Union of India, (1969) 2 SCC 554, the forfeiture of security was upheld by the High Court, the amount forfeited being held as no unreasonable under Section 74 of the Contract Act. The Supreme Court set aside the order of the High Court accepting the plea that the loss suffered by the respondent therein was capable of being measured and they could not seek protection under the garb of Section 74 of the Contract Act. Since the respondent had led no evidence that it had suffered  loss, it was held that the amount could not be forfeited.

 

(C)     Union of India vs. Raman Iron Foundry, (1974) 2 SCC 231. The claim for liquidated damages for all practical purposes were held to stand on the same footing as the unliquidated damages in The claim of unliquidated damages was, thus, held not to give rise to a debt until the liability is adjudicated and damages assessed by a decree or order of a court or other adjudicatory authority. The appellant was held not to have any right or authority to appropriate amounts of other pending bills of the respondent towards satisfaction of claim for damages against the respondent. The breach of contract does not instant incur any pecuniary obligations, nor does the party complaining of the breach become entitled to a debt due from the other party. The only right which accrues at that moment is that the party aggrieved by the breach of contract has a right to sue for damages. Thus, when damages are assessed, the court in the first place must decide that the defendant is liable and then it proceeds to assess as to what is the damage.

 

(D)     In State of Karnataka vs. Shree Rameshwara Rice Mills, (1987) 2 SCC 160, that there has to be an admission of the breach of condition and thereafter only the issue of quantification of damages would arise. Having set out the aforesaid judgements, we consider it appropriate at this stage to refer to the Privy Council pronouncements in Bhai Panna Sing & Ors. Vs. Firm Bhai Arjan Singh-Bhajan Singh- Surjan Singh & Ors., 117 Indian Cases 485 PC, where while dealing with the issue of damages, Atkin, J. observed that the effect of Section 74 of the Contract Act is to disentitle the plaintiffs to recover simpliciter a sum by ways of liquidated damages and that the plaintiff must first prove the damages they have suffered.

(E)     In Indian Oil Corporation vs. Lloyds Steel Industries Ltd., 2007 (4) Arb. LR 84: 2010 (4) R.A.J 263 (Delhi) the Indian Oil Corporation (for short ‘IOC’) invoked a clause in the GCC for liquidated damages and recovered the maximum damages possible even though the work was completed to the satisfaction of the IOC but there was delay in the execution of the work.  This recovery was resisted by the contractor on the ground that there was no damage payable. The dispute was resolved in the arbitration by an award which held that there was absence of justification in invoking the clause of damages. It is at the stage of consideration of objections that the learned single Judge, A.K.Sikri, J. (as he then was) of this Court held that it would be preposterous on the part of the petitioner to submit that it should get the liquidated damages stipulated in the contract even when  no loss is  suffered. Time was essence of the contract providing for 16 months for completion of the work. This period was fixed keeping in view that the terminal at Jodhpur would be ready by that time and the pipeline would reach the said terminal. Thus, while granting extensions, IOC realized that the terminal was not complete and, thus, it could not be put to any use. The period of six (6) months was, thus, held to have lost its significance inasmuch as setting up of Jodhpur Terminal was part of an integrated project and the Terminal could not be put to commercial use before August, 1996, while the contractor had successfully completed the work well before that date. It would be useful to reproduce the observations made in paragraphs 41 & 42, which read as under:

 

It is clear from the above that section 74 does not confer a special benefit upon any party, like the petitioner in this case. In a particular case where there is a clause of liquidated damages the Court will award to the party aggrieved only reasonable compensation which would not exceed an amount of liquidated damages stipulated in the contract. It would not, however, follow there from that even when no loss is suffered, the amount stipulated as liquidated damages is to be awarded. Such  a clause would operate when loss is suffered but it may normally be difficult to estimate the damages and, therefore, the genesis of providing such a clause is that the damage are pre-estimated. Thus, discretion of the Court in the matter of reducing the amount of damages agreed upon is left unqualified by any specific limitation. The guiding principle is ‘reasonable compensation’. In order to see what would be the reasonable compensation in a given case, the Court can adjudge the said compensation in that case. For this purpose, as held in Fateh Chand (supra) it is the duty of the Court to award compensation according to settled principles. Settled principles warrant not to award a compensation where no loss is suffered as one cannot compensate a person who has not suffered any loss or damage. There may be cases where the actual loss of damage is incapable of proof; facts may be so complicated that it may be difficult for the party to prove actual extent of the loss of damage.  Section 74 exempts him from such responsibility and enables him to claim compensation in spite of his failure to prove the actual extent of the loss or damage, provided the basic requirement for award of ‘compensation’, viz., the fact that he has suffered some loss of damage is established. The proof of this basic requirement is not dispensed with by Section 74. That the party complaining of breach of contract and claiming compensation is entitled to succeed only on proof of ‘legal injury’ having been suffered by him in the sense of some loss or damage  having been sustained on account of such breach, is clear from Section 73 and 74. Section 74 is only supplementary to Section 73, and it does not make any departure from the principle behind Section 73 in regard to this matter. Every case of compensation for breach of contract has to be dealt with on the basis of Section 73. The words in Section 74 ‘Whether or not actual damage or loss is proved to have been caused thereby’ have been employed to underscore the departure deliberately made by the Indian legislature from the complicated principles of English Common Law, and also to emphasize that reasonable compensation can be granted even in a case where extent of actual loss or damage is incapable of proof or not proved. That is why Section 74 deliberately states that what is to be awarded is reasonable compensation. In a case when the party complaining of breach of the contract has not suffered legal injury in the sense of sustaining loss of damage, there is nothing to compensate him for; there is nothing to recompense, satisfy, or make amends. Therefore, he will not be entitled to compensation (see State of Kerala v. United Shippers and Dredgers Ltd., AIR 1982 Ker 281). Even in Fateh Chand (Supra) the Apex Court observed in no uncertain terms that when the section says that an aggrieved party is entitled to compensation whether actual damage is proved to have been caused by the breach or not, it merely dispenses with the proof of actual loss or damage’. It does not justify the award of compensation whether a legal injury has resulted in consequence of the breach, because compensation is awarded to make good the loss or damage which naturally arose in the usual course of things, or which the parties knew when they made the contract, to be likely to result from the breach. If liquidated damages are awarded to the petitioner even when the petitioner has not suffered any loss, it would amount to ‘unjust enrichment’, which cannot be countenanced and has to be eschewed.

 

 

(F)In Vishal Engineers & Builders vs. Indian Oil Corporation Ltd., 2012 (2) R.A.J. 390, the Division Bench of the Delhi High Court on considering Sections 73 and 74 of the Contract Act, the decisions rendered by the Supreme Court in Fateh Chand vs. Bal Kishan Das (1964) 1, SCR, 515 and Maula Bux vs Union of India, (1969) 2 SCC, 554, Union of India vs. Raman Iron Foundry (1974) 2 SCC 231 and a decision of the Privy Council in Bhai Panna Singh & Ors. Vs. Firm Bhai Arjan Singh-Bhajan Singh Surjan Singh, 117, Indian Cases, 485 (Privy Council) and decision of the Delhi High Court in Indian Oil Corporation vs. Lloyd Steel Industries Ltd. (2007) 4 Arb. LR, 84, held that the liquidated damages stipulated in the contract are not payable, as the complaining party has not suffered any loss. In this regard the Delhi High Court observed as under:

“12. Section 73 of the Contract Act, thus, contemplates award of damages for losses suffered by breach of contract by the opposite party. Section 74 of the Contract Act stipulates that in case  of such a broken contract if a sum is named in the contract as the amount to be paid in case of such breach, whether or not actual damage or loss is proved to have been caused thereby, the aggrieved party is entitled to receive from the opposite party who has broken the contract, a reasonable compensation not exceeding the amount so named.

13.         The question which, thus, arises is whether in view of such a  stipulated amount  damages  are liable to be paid ipso facto without any further proof qua issue of sufferance of damages or quantification or something more is required to be done.

 

The duty of the court not to enforce the penalty clause, but only to award reasonable compensation has been held to be statutorily imposed upon courts by Section 74 of the Contract Act. The court just has to adjudge in every case, reasonable compensation for breach of contract having regard to the conditions which existed on the date of the breach [ref: Fateh Chand case (supra)]

 

(G)     In Indian Oil Corporation vs. M/s Lloyds Steel Industries Ltd., (2007) 4 Arb. LR 84, the Delhi High Court held as under:

“38. Notwithstanding the above, the petitioner still wants damages to be recovered from the respondent on the spacious plea that liquidated damages mentioned in the contract are predetermined damages and, therefore, in view of provisions of Section 74 of the  Indian  Contract Act, the petitioner  was entitled to these damages  and it was necessary for the petitioner to prove these damages. The legal position, as explained by the Supreme Court in ONGC v. Saw Pipes (Supra), which has already explained above, is not in doubt.  However, it is only when there is a loss suffered and once that is proved, it is not for the arbitrator or the Court to examine the actual extent of the loss suffered once there is a pre-estimation thereof. Moreover, the compensation, as stipulated in the contract has to be reasonable. In a particular case where the defaulting party is able to demonstrate that delay/default has not resulted in any loss being suffered by the other party, then that party cannot claim the damages only because in the contract there is a stipulation regarding liquidated damages. The Supreme Court in ONGC v. Saw Pipes (Supra) referred its earlier judgment in the case of Fateh Chand (supra) and Mula Bux (Supra).

(H)                   Kailash Nath Associates vs DDA, (2015) 4 SCC 136

The Petitioner Kailash Nath was declared as the successful bidder by respondent in relation to auction proceedings of a plot of land. The Petitioner had deposited 25% of the bid money as earnest money. However, without giving notice to the Petitioner, the respondent cancelled the bid and forfeited the earnest money deposited by it. 

In the above facts and circumstances, the Supreme Court held that it would be arbitrary for respondent to forfeit the earnest money on two fundamental grounds. First, there is no breach of contract on part of the appellant and second, respondent not having been put to any loss, even if it could insist on a contractual stipulation in its favour, it would be arbitrary to allow respondent as a public authority to appropriate earnest money without any loss being caused.  In the judgment, the Supreme Court restated the principles applicable to Section 74. In doing so, the Court held that, “…like Section 73 and 75 of Contract Act, 1872, compensation is payable for breach of contract under Section 74 … only where damage or loss is caused by such breach”. The Court also held that, “…damage or loss caused is a sine qua non for the applicability of Section 74”.

 

It is clear from the above that Section 74 does not confer a special benefit upon any party. Where there is a clause of liquidated damages the Court will award to the party aggrieved only reasonable compensation which would not exceed an amount of liquidated damages stipulated in the contract. It would not, however, follow therefrom that even when no loss is suffered, the amount stipulated as liquidated damages is to be awarded. Such a clause would operate when loss is suffered but it may normally be difficult to estimate the damages and, therefore, the genesis of providing such a clause is that the damages are pre-estimated. Thus, discretion of the Court in the matter of reducing the amount of damages agreed upon is left unqualified by any specific limitation. The guiding principle is ‘reasonable compensation’

As regards adequacy of compensation in a given case, the court can adjudge the said compensation in case to case basis. As held in Fateh Chand (supra) it is the duty of the Court to award compensation according to settled principles. Where no loss is suffered, one cannot compensate a person who has not suffered any loss or damage. Moreover, there may be cases where the actual loss or damage is incapable of proof; or facts may be so complicated that it may be difficult for the party to prove actual extent of the loss or damage.

No doubt,  Section 74 stipulates that to claim compensation even if tangible evidence is not forthcoming, still, if the basic requirement for award of ‘compensation’, viz. the fact that he has suffered some loss or damage is established, compensation can still be grated. The proof of this basic requirement is not dispensed with by Section 74. That the party complaining of breach of contract and claiming compensation is entitled to succeed only on proof of legal injury having been suffered by him in the sense of some loss or damage having been sustained on account of such breach, is clear from Sections 73 and 74. Section 74 is only supplementary to Section 73, and it does not make any departure from the principle behind Section 73 in regard to this matter. Every case of compensation for breach of contract has to be dealt with on the basis of Section 73. The words in Section 74 ‘whether or not actual damage or loss is  proved to have been caused thereby’ have been employed to underscore the departure deliberately made by Indian legislature from the complicated principles of English Common Law, and also to emphasise that reasonable compensation can be granted even in a case were extent of actual loss or damage is incapable of proof or not proved.

One may note that Section 74 states that what is to be awarded is reasonable compensation. It appears to be a deliberate inclusion. In a case when the party complaining of breach of the contract has not suffered legal injury in the sense of sustaining loss or damage, there is nothing to compensate him for; there is nothing to recompense, satisfy, or make amends. Therefore, he will not be entitled to compensation (see State of Kerala v. United Shippers and Dredgers Ltd., AIR 1982 Kerala 281). Even in Fateh Chand (supra) the Apex Court observed in no uncertain terms that when the section says that an aggrieved party is entitled to compensation whether actual damage is proved to have been caused by the breach or not, it merely dispenses with the proof of ‘actual loss or damage’. It does not justify the award of compensation whether a legal injury has resulted in consequence of the breach, because compensation is awarded to make good the loss or damage which naturally arose in the usual course of things, or which the parties knew when they made the contract, to be likely to result from the breach. If liquidated damages are awarded to the petitioner even when the petitioner has not suffered any loss, it would amount to ‘unjust enrichment’, which cannot be countenanced and has to be eschewed.



REMARK

From the foregoing what therefore emerges is that parties to a contract that, in the event of breach, the party in default shall pay a stipulated sum of money to the other. However, the stipulated sum has to be a genuine pre-estimate of damages likely to flow from the breach and is termed as ‘liquidated damages’. It thus flows that if it is not a genuine pre-estimate of the loss, but an amount intended to secure performance of the contract, it may be a penalty.

Interestingly, in Fateh Chand  (supra),  the  Supreme  Court  explained this principle in the following words:

“…Section 74 declares the law as to liability upon breach of contract, where compensation is by agreement of parties predetermined or where there is a stipulation by way of penalty. But the application of the enactment is not restricted to cases where the aggrieved party claims relief as a plaintiff. The section does not confer a special benefit upon any party. It merely declares the law that notwithstanding any term in the contract for determining the damages or providing the forfeiture of any property by way of penalty, the court will award to the party aggrieved only reasonable compensation not exceeding the amount named or penalty stipulated.”

The court also observed:

“The court has to adjudge in every case reasonable compensation to which the plaintiff is entitled from the defendant on breach of the contract. Such compensation has to be ascertained having regard to the conditions existing on the date of breach. The measure of damages in the case of breach of a stipulation by way of a penalty is by section 74 reasonable compensation not exceeding the penalty stipulated for. In assessing damages the court has, subject to the limit of the penalty stipulated, jurisdiction to award such compensation as it deems reasonable having regard to all the circumstances. Jurisdiction of the Court to award compensation in case of breach of contract is unqualified except as to the maximum stipulated; but compensation has to be reasonable, and imposes upon the court a duty to award compensation according to settled principles.”

                                              -------

Anil K Khaware

Founder & Senior Associate

Societylawandjustice.com

No comments:

Post a Comment

ORDER XXX CPC- PROVISIONS FOR SUIT BY INDIGENT PERSONS

  ORDER XXXIII CPC- PROVISIONS FOR SUIT BY Indigent personS In the Courts of law, while filing suits of various nature, in terms of Courts...