Sunday, May 7, 2023

DAMAGES & MITIGATION OF LOSSES UNDER CONTRACTS

 


DAMAGES & MITIGATION OF LOSSES UNDER CONTRACTS

 

The backbone of any arrangement and/or commercial transaction is contract. The agreement enforceable in law shall be contract. The requisites of agreement is too well known to require elucidation. Still, to recapitulate, sections 2 (h) of Indian Contact Act 1872 defines contract and the foremost requisite of it is acceptance of terms of offer by  persons of sound mind, and they should have capacity to enter into agreement and is not declared insolvent and otherwise capable of entering into contract and still, the agreement/contract is not against public policy. Thus, the pre-requisites of a contract has to cross the threshold as illustrated above. However, the broad contour of the discussion here shall revolve around the aspect of breach of contract and consequential claim of damages, law in that regard, besides, what are the obligation of contracting parties are deliberated.

The basic object of the contract is to set out in clear term, the respective obligation of parties. The document as a reminder shall consistently convey to the parties the respective covenants to be met by the parties. The purpose of the contract therefore is preemptive as well. The breach occurs, when a party to a contract does not fulfill its obligation. If breaches occurs the losses are the most likely result to the other party. Though, breaches of obligation could be for variety of reasons such as due to force measure like act of god and situation beyond control of contracting parties. These are exception to convention. What if the breach does not occur due to force measure, but to subvert the contract and breach the obligation for material gains. What liability in such an event shall be cast on defaulting party. Yet again, whether , any default shall in itself tantamount to breach? Moreover, what remedy does the other party shall have in the event of breaches by the defaulting party? Whether Section 73,74 and 75 of Indian Contract Act shall answer all such elements has to be found out. Another aspect would be, if a party to the contract suffers losses due to the breaches by a defaulting party, whether any corresponding obligation is also cast on a party not in breach, in order to raise a tenable claim in courts of law. The law has thus, evolved wherein it is required of a party not in breach to try and make effort to mitigate the losses arising due to breaches of defaulting party and the sufferer may claim remainder of losses which could not be mitigated even after due diligence and that shall fall within the parameter of doctrine “Mitigation of Losses”     

No doubt the basic objective of a contract is to discerningly specify what are the terms or covenants agreed upon by the parties. In the event of disputes, the probable litigation could be avoided if the parties understands their respective fault line. The breach of contract if alleged may lead to cancellation of instruments and/or the party who suffered may seek injunction and damages. In order to claim damages, the party claiming damages shall have to prove that wrong or breaches are committed by the other party i.e defaulting party or parties and owing to the breaches the party who suffered the breach shall be entitled to damages. However, the damages, as claimed should be proximate, approximate or the one which may have direct bearing to breaches. However, another terrain, which is equally important is that a party who suffered losses or likely to suffer losses, whether the efforts were made by such party to mitigate the losses so as to reduce the burden of opposite party. That follows whether a party who suffered losses have initiated or taken all such plausible steps to reduce the prospective losses or not? This is a legal mandate for claiming damages. What therefore may emerge is whether an unsuccessful
litigants shall have to inevitably compensate a successful claimant? It is not so as a matter of course. What would be necessary is to show direct bearing of the act or conduct of defaulting party in causing losses to the other party. It therefore follows that is  a party to a contract sits idle with  a view to seek accumulation of damages so as to claim compensation on higher side, that will not be permissible. There cannot be premium to idleness. The action or reaction of the party staring at losses or prospective losses shall have to act promptly. The pith and substance of the doctrine of “mitigation of losses”  is that if a person who has sustained or suffered an injury or loss should take all such plausible or reasonable steps so as to avoid any further injury or loss. Thus, responsibility is cast on a party to make all efforts and that too at the earliest to mitigate the losses so as to minimize the claim. The basic doctrine of contract is that the non-breaching party should mitigate damages or risk.

What if no efforts are made or no reasonable steps are taken by non breaching party for mitigating losses? In such an event the breaching party may take defence that as the non breaching party have failed to mitigate their loss therefore, lenient view may be taken against the breaching party in an effort to
reduce the level of damages. Generally, courts are sympathetic to the efforts made by a claimant seeking to deal with a breach of contract.

It shall be incumbent on the party to the alleged breach, i.e more oftently the defendant shall have to discharge the burden of proving that the plaintiff or claimant has failed in its duty to make efforts for mitigation of loss. These are question of fact. Conversely, the plaintiff shall have the burden of proving that defendant should prove that the plaintiff should have mitigated the loss and it was in the command of the plaintiff to do so. It is a settled proposition in law that duty is cast on an innocent party to mitigate the loss it has suffered. There is no straight jacket formula about the steps taken in this regard. That will depend on the facts and circumstances of each case. Suffice however to show that reasonable or plausible steps were taken for mitigating the losses. If plaintiff/claimant is able to prove that steps were taken for mitigation of losses, then even reasonable costs for mitigation may be recovered from defendant.

SECTION 73-75 of INDIAN CONTRACT ACT 1872

 

The Indian Contract Act 1872 contains a comprehensive provision about damages and as regards duty about mitigation of losses. Section 73 of Indian Contract Act 1872 may be reproduced as under:

Section 73: Compensation for loss or damage caused by breach of contract.

73. When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it.

Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach.

Compensation for failure to discharge obligation resembling those created by contract.—When an obligation resembling those created by contract has been incurred and has not been discharged, any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default, as if such person had contracted to discharge it and had broken his contract.

Explanation.—In estimating the loss or damage arising from a breach of contract, the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account.

 

The very expression 'the means which existed of remedying the inconvenience'  implies that a duty is cast upon a person complaining of a breach of contract, to use reasonable prudence and common sense and should take all probable steps available in order to mitigate the loss arising owing to the breaches of defaulting party.

The test of reasonableness: It implies that under the given circumstances whether a prudent man would act in a manner as the claimant has acted. In other words, assuming that wrong would have been caused by claimant himself, whether he would have acted in a same manner or not shall be the yardstick.

INTERPRETATION OF THE DOCTRINE OF DAMAGES

The plaintiff in order to be entitled to claim damages on the breach of contract must take reasonable steps to mitigate the loss arising on account of such breach/es.” It means that whether the plaintiff has taken steps to mitigate the loss or not shall be a determinative factor for assessing damages. If the plaintiff fails in duty to mitigate, the loss of the damages claimed by him may be construed as if it has not arisen naturally and in the usual course of situation. What is of paramount importance in the context is that the person who has breached the contract should not suffer the burden of additional damages which could be prevented had the claimant acted diligently and if reasonable efforts were made in time to mitigate the damage. This clearly means that plaintiff should not get more than the loss suffered and that too after acting reasonably with a view to mitigate damages.

 

There are Three (3) basic rules enunciated about mitigation of losses:

(i)              The plaintiff cannot recover the loss consequent upon the default of the defendant, if the plaintiff did not avoid the loss by taking reasonable steps.

(ii)             If the plaintiff avoids or mitigates the loss, he cannot recover more than what was reasonably required of him.

(iii)           Where the plaintiff suffers loss or incurs expense by taking reasonable steps to avoid or mitigate the loss resulting from the defendant’s default, he may recover further loss or expense from the defendant.

No doubt, the plaintiff can also recover expenses or further loss incurred by him in taking reasonable steps to mitigate his loss resulting from the defendant’s breach. Such a claim can be raised even when the steps for mitigation were unsuccessful or in fact may have accentuated the losses.

Section 73 of the Indian Contract Act, 1872 prescribes grant of unliquidated damages, whereas Section 74 provides liquidated damages. The unliquidated damages are not quantified and, may be  awarded through the courts of law after evaluation of loss or damages that may have been incurred due to the acts of defaulting party, Whereas, Liquidated Damages are the damages which the parties specify in the contract.

DUTY IN CASE OF BREACH OF CONTRACT


The claimant has certain duty in case of any breach of contract. Failure to mitigate loss may prevent the innocent party from recovering damages for avoidable loss. Defendants often assert that claimants have failed to mitigate their loss in an effort to reduce the level of damages. Generally, courts are sympathetic to the efforts made by a claimant seeking to deal with a breach of contract. The requirement to take ‘reasonable steps’ is not a high standard. In particular, the courts will typically reject criticism of a claimant seeking to do its best to mitigate its loss when faced with a breach of contract, particularly when decisions have to be made – often quickly – by a claimant with imperfect knowledge. It is, after all, the defendant that has put the claimant in the position of having to deal with a breach of contract. However, the courts will penalize a claimant in damages where it has demonstrably and unreasonably failed to take any steps to mitigate its loss, or where the steps that it has taken are clearly inadequate. In circumstances where a claimant could, for example, potentially mitigate its loss by selling goods in the market, the court will usually expect to see evidence of meaningful
attempts to do so. That should not be difficult if such attempts are genuine. A claimant that gives the impression that it is more concerned with enhancing a claim than mitigating loss should expect deductions in the damages awarded to it.

BURDEN OF PROOF ON DEFENDANT

It is the defendant who has the burden of proving that the claimant has failed in its duty to mitigate loss. What exactly the claimant is required to do with respect to mitigation is an issue of fact. The Court, for instance, will require that the insured person act reasonably in seeking out medical treatment to get better, but will not require the claimant to undergo surgery or treatment which is dangerous or futile or where the likelihood of a successful outcome is uncertain. While the plaintiff has the burden of proving the breach of contract, the defendant must prove that the plaintiff could have and should have mitigated the loss.  

Following a breach of contract, the innocent party has a duty to mitigate the loss it has suffered. This duty requires reasonable steps to be taken to limit the losses that are incurred (and also to avoid incurring unnecessary expenditure seeking to remedy the breach). A claimant cannot simply sit on its hands watching losses accumulate with the intention of recovering them in full from the defendant. However, a claimant need not take unusual steps that would be outside the normal course of business, or even incur undue costs. The reasonable costs of mitigation are recoverable from the defendant.

                               

   LAW

In a landmark case Fateh Chand vs Balkishan Das  AIR 1963 SC1405 the hon’ble Supreme Court of India postulated that the aggrieved party is entitled to appropriate compensation, not to exceed the amount of the penalty or the amount pre-determined to be paid following the violation of the contract. The Supreme Court has further held that application of these laws is not limited to any circumstances. What thus, emerges are as under:

(i)            If the amount payable substantially more than the likely harm for breach of the contract, id It is a penalty.

(ii)          If a contract specifies a sum payable on a specific date and also additional sum, if a default occurs, such additional value may be referred to as a penalty.

(iii)         The court shall be the ultimate arbiter to determine if the sums shall be “penalty” or “damages,” in the appropriate cases.

 

The very object of such clauses are to prescribe certainty. The risk and cost are needed to be adequately contemplated and defined and in the event harm is caused these clauses shall have to be referred to for seeking damages.

In Kailash Nath Associate Vs DDA (2015) 4 SCC 136, the Supreme Court has considered some important questions relating to section 74 of the Indian Contract Act 1872. In fact, the conclusion of the apex court has an obvious departure from some well-known principles of contract law, the case warrants close attention. Section 74, of course, provides that the claimant in a breach of contract case is entitled to ‘reasonable compensation’ not exceeding the sum named in the contract as payable in the event of breach. This was an intentional departure from the distinction traditionally drawn by the common law or equity between penalties and liquidated damages.

It may be worthwhile to refer to in nutshell , the circumstances in Kailash Nath (Supra).In an  auction conducted by the Delhi Development Authority (‘DDA’) Kailash Nath Associates’ (‘KNA’) had offered bid for one of the plots and it was accepted. A sum of Rs. 78 Lakhs i.e equivalent to 25% of auction value was paid as earnest money. The terms of auction stipulated that DDA was entitled to forfeit this amount in case of any default, breach or non-compliance of any of the terms and conditions of the auction.  One of these terms was that KNA had to pay the remaining 75% within three months. This KNA was unable to do so, but DDA, at its request, extended the deadline on the understanding that KNA would pay 18% interest. Eventually, some six years after the bid was accepted, DDA decided to forfeit the earnest money and cancelled the allotment. It then re-auctioned the property and was able to sell it for around Rs. 11 crores, nearly three times the amount KNA had agreed to pay. KNA sought specific performance and, in the alternative, a refund of
the earnest money. The specific performance claim failed but it is held that it was entitled to a refund.

The Supreme Court has considered the factor that DDA had in fact reaped advantage as the plot was sold to a price three times higher than earlier auction price. Therefore, if the earnest money deposited by KNA was to be forfeited, the DDA would have unduly and wrongfully enriched itself and that was held as contrary to basic principles of damages in as much as damages can only be given for as compensation for damage or loss suffered. If damage or loss is not suffered, the law does not provide for a windfall. The Supreme Court had also granted 9% p.a interest to KNA, rather than 7% as prescribed in contract. It was so, because DDA having chosen to contest the case vigorously even on refund of earnest money, when no loss caused to it, shall stands on a different footing.

The requirement to take ‘reasonable steps’ is not a high
standard. In particular, the courts will typically reject criticism of a claimant seeking to do its best to mitigate its loss when faced with a breach of contract, particularly when decisions have to be made – often quickly – by a claimant with imperfect knowledge. It is, after all, the defendant that has put the claimant in the position of having to deal with a breach of contract. However, the courts will penalize a claimant in damages where it has demonstrably and unreasonably failed to take any steps to mitigate its loss, or where the steps that it has taken are clearly inadequate. In circumstances where a claimant could, for example, potentially mitigate its loss by selling goods in the market, the court will usually expect to see evidence of meaningful attempts to do so. That should not be difficult if such attempts are genuine. A claimant that gives the impression that it is more concerned with enhancing a claim than mitigating loss should expect deductions in the damages awarded to it.

CONCLUSION

The law of damages as evolved over the years has some basic principles i.e., A party who claims breach of contract by a defaulting party must take all such measures as may be deemed reasonable in the circumstances so as to mitigate the loss. A claimant shall be entitled to claim damages on account of breach of contract only if the claimant has taken all plausible steps to mitigate the loss arising out of such breach or breaches. The claim of damages shall not be awarded to a party sitting idle, but it will be expected of a suffering party that all reasonable steps were taken by him with a view to mitigate the loss. If a suffering party fails to take such measures as narrated above, the party in breach may claim reduction in the claim of damages of sufferer.           

It is thus incumbent on the claimant to take all reasonable steps to mitigate the losses as soon as the claimant came into the knowledge of a breach. This will be a relevant/ determining factor for awarding damages. There may also be a situation where damages may be caused to a claimant in the natural course of events, in such an event the claimant shall be obligated to carry out rectification or repairs themselves, rather than allowing their damage to accentuate by remaining oblivious to it. However , it also follows that a claimant will not be required to act against the interests of innocent parties to reduce recoverable loss. Further, the claimant is not required to sacrifice their commercial reputation in order to avoid losses suffered by a breach of contract.

                                           -----------

                                  Anil K Khaware

Founder & Senior Associate

Societylawandjustice.com

 

 

 

 

No comments:

Post a Comment

ORDER XXX CPC- PROVISIONS FOR SUIT BY INDIGENT PERSONS

  ORDER XXXIII CPC- PROVISIONS FOR SUIT BY Indigent personS In the Courts of law, while filing suits of various nature, in terms of Courts...