Friday, January 17, 2025

ARBITRATION-TERMINABLE AGREEMENT AND INJUNCTION U/S 9 OF A & C ACT

 


Arbitration-Terminable agreement and injunction u/s 9 OF A & C Act

The Section 9 of Arbitration & Conciliation Act 1996 (as amended and up to date) is quite significant with a view to accord interim protection to a party to the lis and subject to arbitration dispute. The power of the courts are though quite limited in this regard and as a short term measure interim protection accorded could be accorded to aggrieved party, if the case is otherwise made out. The ultimate remedy however shall be subj3ct to the decision by the Arbitrator u/s 17 of Arbitration & Conciliation Act 1996 and till the pendency of arbitral proceedings and till it culminates in publication of award, the interim protection or order of injunction passed by the Arbitrator may continue. There is another dimension which shall be emphasized herein i.e whether any injunction against an agreement already terminated could be sought and effect of such termination could be relegated back. In other words whether u/s 9 of A & C Act whether even the termination notice could be set quashed or aside or whether any order of injunction restraining the respondent from giving effect to termination notice could be passed? What may follow hence is that assuming termination to be illegal, whether, the same could be set aside or restrain order could be passed by a competent court u/s 9 of the A & AC Act? This aspect shall further be deliberated herein. It may be apt to reproduce the provision for reference before proceeding further. The same is as under:

Section 9: Interim measures, etc., by Court.

- [(1)] [Renumbered as sub-section (1) by Act No. 3 of 2016 dated 31.12.2015.-] A party may, before or during arbitral proceedings or at any time after the making of the arbitral award but before it is enforced in accordance with section 36, apply to a Court:

(i) for the appointment of a guardian for a minor or a person of unsound mind for the purposes of arbitral proceedings; or

(ii) for an interim measure of protection in respect of any of the following matters, namely:-

(a) the preservation, interim custody or sale of any goods which are the subject-matter of the arbitration agreement;

(b) securing the amount in dispute in the arbitration;

(c) the detention, preservation or inspection of any property or thing which is the subject-matter of the dispute in arbitration, or as to which any question may arise therein and authorising for any of the aforesaid purposes any person to enter upon any land or building in the possession of any party, or authorising any samples to be taken or any observation to be made, or experiment to be tried, which may be necessary or expedient for the purpose of obtaining full information or evidence;

(d) interim injunction or the appointment of a receiver;

(e) such other interim measure of protection as may appear to the Court to be just and convenient,

and the Court shall have the same power for making orders as it has for the purpose of, and in relation to, any proceedings before it.

(2 )  Where, before the commencement of the arbitral proceedings, a Court passes an order for any interim measure of protection under sub-section (1), the arbitral proceedings shall be commenced within a period of ninety days from the date of such order or within such further time as the Court may determine.

(3) Once the arbitral tribunal has been constituted, the Court shall not entertain an application under sub-section (1), unless the Court finds that circumstances exist which may not render the remedy provided under section 17 efficacious.] 

It is observed that often the situation portrayed in this regard is that any predetermined action in illegally terminating agreement shall always be amenable to restrain order under Section 9 of A & C Act and if the action is replete with mala fide, the courts are not powerless in passing restrain order u/s 9 of A & C Act.

It is no res integra that a determinable contract can always be determined and no fetter could be attached thereto. Generally speaking no specific performance could be granted in respect of determinable contract, more so in the proceedings u/s 9 of A & C Act 1996. In any event, any declaration to the effect that termination notice was bad in law would be the ultimate relief and this could be adjudicated only by Arbitral Tribunal. It may further appear that if the contract is determinable, and terminated by one party, Section 14 (1) of Specific Relief Act 1963 comes in and the contract cannot be revived or restored by a Court and specific performance cannot be enforced. Reliance in this regard are as under:

(i)          Planet M Retail Limited Vs Select Infrastructure Pvt Ltd [2014 SCC Online Del 4869

(ii)        MIC Electronics Ltd Vs Municipal Corporation of Delhi (2011) 1 Arb LR 418 (DB)

(iii)       Rajasthan Breweries Ltd Vs The Stroh Brewery Company 2000(55)DRJ (DB)

(iv)       VF Services (UK)Ltd Vs Union of India & Ors 2011 X AD (Delhi) 268

(v)         Bharat catering Corporation Vs Indian Railway catering and Tourism Corporation Ltd (IRCTC) and Ors 164 (2009) DLT 530

The Delhi High Court had to deal with in RPS Educational Society (Regd) Vs DDA OMP 538/2008 with the following prayer u/s 9 of A & C Act as under:

“5. It appears that in terms of license deed, the respondent has authority to cancel the license. Under Section 9 of the Arbitration & Conciliation Act, the Court can pass an interim order to preserve such subject matter of dispute which it considered was necessary to be preserved for adjudication of the dispute. However, an order under section 9 of the A & C Act cannot be passed by the Court directing specific performance of the contract, the breach of which is alleged by the petitioner. This Court in Excel Generators Pvt Ltd Vs IJ M Corporation Berhead OMP No. 241/09( decided on 13th May 2009) had observed that where a contract is terminable contract and it can be foreclosed, the interim relief under section 9 of the A & C Act cannot be granted for specific performance of the contract. In all those cases where monetary damages can compensate the breach of contract, the Court cannot insist upon the parties that the contract should be specifically enforced”. 

The Division bench of Delhi High Court in Rajasthan Breweries Ltd Vs The Stroh Brewery Company 2000(55)DRJ (DB) has held as under:

19. Even in the absence of specific clause authorizing and enabling either party to terminate the agreement in the event of happening of the events specified therein, from the very nature of the agreement, which is a private commercial transaction, the same could be terminated even without assigning any reason by serving a reasonable notice. At the moist, in case, ultimately it is found that termination was bad in law or contrary to the terms of the agreement or of any understanding between the parties or for any other reason the remedy of the appellant would be to seek specific performance of the agreement and for that view of the matter learned single judge was justified in coming to the conclusion that the appellant had sought for an injunction seeking to specifically enforce the agreement. Such an injunction is statutorily prohibited with respect of a contract which is determinable in nature. The application being under the provision of Section 9 (ii)(e) of the A & C Act, relief was not granted in view of Section 41 (i)© read with Section 41 of the Specific relief Act. It was righty held that other clauses of section 9 of the Act shall not apply to the contract, which is otherwise determinable in respect of which the prayer is made specifically to enforce the same”.

In Bharat catering Corporation Vs Indian Railway catering and Tourism Corporation Ltd (IRCTC) and Ors 164 (2009) DLT 530 it is held by the Division bench of Delhi high Court that:

“5…the scope and ambit of Section 9 is not to restore the contract which has already been terminated. The contract between the respondent and the petitioner created a commercial relationship between the parties. The termination of contract is one of the factors of the contract and as per contract entered into between the parties, the contract could be terminated by the respondent by respondents for various reasons given therein. If the petitioner is aggrieved by the act of the termination of the contract by respondent and considers that the termination was bad or illegal, the petitioner is at liberty to invoke the arbitration clause and claim damages if any, suffered by the petitioner. The contract cannot be restored by the Court under Section 9 nor is it a case where the Court should interfere. In my view prima facie there is no case made out in favour of the petitioner. The petitioner’s conduct as reflected from the impugned letter of termination justifies termination of the contract.”

M/s Sundaram Finance Limited Vs M/s NEPC India Ltd AIR 1999 SC 565

Firm Ashok Traders vs Gurumukh Das Saluja AIR 2004 SC 1433.

In Sundaram Finance (Supra) and Firm Ashok (Supra) it is held that while preferring Section 9 petition, there should be manifest intention and action for seeking invocation of arbitration clause and steps taken in this regard.

The Delhi High Court in a matter captioned as M/s Inter ADS Exhibition Pvt Ltd Vs Busworld International Cooperative Venootschap Met Beperktee Anasprakelijheid had to deal with the following prayer us 9 of A & C Act.

(a) The termination notice dated 15.03.2019 issued against the terms of JVA-II, be quashed and set aside;

(b)  Pass ex-parte interim orders(s) restraining the Respondent to give effect to the termination notice dated 15.03.2019

The Delhi High Court in M/s Inter ADS Exhibition Pvt Ltd (Supra) bearing no. OMP(I) (Comm) 273/2019. In para 40 it is held as under:

“40. Section 41 (e) of Specific Relief Act 1963 (SRA) further provides that an injunction cannot be granted to prevent breach of a contract, the performance of which would not be specifically enforced. In my view the contract between the parties to terminate the same, on breach of the obligation under the contract, cannot be enforced, the bar u/s 41(e) prevents this Court from granting any injunction. Thus, the first relief prayed by the petitioner is declined”.

In M/s Inter ADS Exhibition (Supra) para 46 and 47 are worthy of reference. The same is as under:

46. A joint venture agreement was terminated by one party to the contract. The Division Bench relying on the judgment in the case of Rajasthan Breweries Ltd ( Supra) as well as Section 14 of the SRA held that once the lease had been terminated, passing of mandatory injunction would amount to first creating an agreement between the parties and then enforcing the same. The Division bench set aside the judgment of ld single judge whereby the ld single judge had by way of an interim measure allowed the running of train under the contract in question on the ground of irreparable loss to the Company and inconvenience to public. The Division bench held that the interim arrangement was neither justified nor legally sustainable….”

47. It is clear that in law, once termination of contact takes effect the operation cannot be stayed by an interim injunction. Thus, the second relief sought in the present petition cannot be granted and is hereby rejected.”

 

The most recent judgment of Delhi High Court in the context is captioned as GHH Bumi Mining Services Pvt Ltd Vs Hindustan Zinc Ltd bearing OMP (I) (Comm) 204/2023 had relied upon ABP Network Private Ltd Vs Malika Malhotra 2021 SCC Online 4733. The disputes arose in respect of execution of a project for providing services to ore body to produce mines at Zwarmala Mine in Udaipur District, Rajasthan. It was an extremely capital intensive project and required huge investments of creating resources and creating of infrastructure. The contract was however terminated. The reliance was placed on ABP Network (Supra) to the effect that:

47. A contract which is determinable, whether by efflux of time or at the option of either of, or both the parties and whether preceded by the requirement of issuance of notice or any other pre-termination formality, or not, is, therefore, to be regarded as “in its nature determinable” within the meaning of Section 14(d) of Specific relief Act.:

In GHH Bumi Mining Services (Supra) it is accordingly held as under:

“27. It was thus held that the remedy, in the event of an illegal termination, would only be seek compensation for wrongful termination and not to maintain a claim for specific performance of the agreement was statutorily prohibited, as they were determinable in nature”  

In GHH Bumi Mining Services (Supra) para 32 shall be of worth reference:

32. The Specific Relief Act 1963 was amended in the year 2018 with the objective to give impetus to the legal regime governing enforceability of contract in India. The pre 2018 amendment position was that specific performance of an agreement was an equitable and discretionary relief but after the 2018 amendment, the words “specific performance of any contract may, in the discretion of the court may be enforced” in section 10 of the Act have been substituted with the words “specific performance of a contract shall be enforced subject to [Section 11(2),14 and 16 of the Act]”. Thus, once the factors mentioned in Section 11(2),14 and 16 of the Act are met, it is obligatory upon the Courts to order specific performance of a contract. Fact however, remains that section 41(e) of the Act provides that an injunction can be grated  “to prevent the breach of a contract which would not be specifically enforced”. Furthermore, section 14(d) of the amended Act provides that a contract which is “in its nature determinable” cannot be specifically enforced. fact remains that a contract which is “in its nature determinable” was incapable of specific performance by virtue of the erstwhile section 14 (1) ( c) continues to remain so even by virtue the present section 14(d)..

Finally in GHH Bumi Mining Services (Supra) it is held as under :

34…The question as to whether the termination was strictly in consonance with the contractual terms or not is not to be looked into by this Court, in elaborate and exhaustive manner. Suffice it to say, prima facie, there are braech-notices herein. Even if it was to be held that the termination was bad in law or contrary to the terms of the agreement or understanding between the parties, the remedy for the petitioner would be to seek compensation for the wrongful termination and therefore, in the garb of interim relief under Section 9 of the said Act, the petitioner cannot claim for specific performance of the Agreement. Such grant of injunction is rather expressly proscribed in case of a contract like the present one”.

The Supreme Court has held in the case captioned as Cotton Corporation Ltd Vs United Industrial bank Ltd & Ors (1983) 4 SCC 625 that Section 41 (b) & other provisions of Specific relief act with reference to grant of interim injunction. It is further held that power to grant temporary injunction conferred in aid or as auxillary to the final relief that may be granted. If the final relief cannot be granted in terms of prayer, temporary relief in the same term can hardly if ever be granted.

On the basis of the aforesaid discussion what clearly emerges is that the relief sought u/s 9 of A & C Act 1996 shall relates to the following:

(i)            Extremely urgent relief;

(ii)          For a short duration;

(iii)         For protecting subject matter, preserving it;

(iv)         Securing money in dispute;

(v)           The intention to initiate arbitration and steps of initiating arbitration should be evident;

(vi)         No relief u/s 9 of A & C Act can be granted for restoring terminated agreement or restrain order against termination notice shall not fall within the domain of section 9.

(vii)        No temporary injunction in respect of the terminable agreement;

(viii)       Section 14 (1 (c) (d) and section 41 of Specific Relief Act shall be applicable;

(ix)         Within a short span , in case interim relief is granted (or not granted), the Arbitral tribunal is to be constituted and the Arbitral tribunal shall be competent to extend or to make absolute interim relief if any or grant interim relief in the first instance .

(x)          The gamut of agreement whether termination was bad or claim of damages, if found payable due to breach shall be the domain of Arbitrator.

                                    --------

                       Anil K Khaware

Founder & Senior Associate

Societylawandjustice.com

 

No comments:

Post a Comment

ARBITRATION-TERMINABLE AGREEMENT AND INJUNCTION U/S 9 OF A & C ACT

  Arbitration-Terminable agreement and injunction u/s 9 OF A & C Act The Section 9 of Arbitration & Conciliation Act 1996 (as amen...